Laindon Neighborhood Centre – Works timeline and deliberate reopening








Basildon Council is now absolutely dedicated to reopening Laindon Neighborhood Centre as quickly as works to make sure the centre is match for goal have been accomplished.

Basildon Council took over the working of Laindon Neighborhood Centre in November 2020 after the keys had been handed to the council by the Laindon Neighborhood Affiliation.

Following a radical buildings inspection it was found the centre was not match for goal. Works are presently underway to convey the constructing again into use and guarantee it’s match for goal and meets the wants of the neighborhood.

That is provisional timeline and additional progress updates can be revealed right here as time goes on.

Works timeline and deliberate reopening as at 08 July 2021

Completion date  / notes Motion Standing
Could 2021

Laindon Neighborhood Centre Situation Survey – Report overview

Accomplished
18  June 2021

Evaluate of Mechanical Companies by Ridge (consultants)

Accomplished
02 July 2021

Asbestos R&D Survey(Authorized requirement for a survey to be undertaken previous to any works commencing)

In Progress
09 July 2021 Asbestos elimination works arising from survey (if any) Works (if any) but to start out

09 July 2021

Scope and charge worth obtained and work now to be commissioned

Scope of works report on Mechanical Companies:

  • Liaise with fuel utility supplier and generate a citation for a re-connection/New connection
  • Generate a scope of works and any drawings.

Proposed Mechanical works:

  • Reconnection of fuel, drain and energy flush the heating system fill and dose, re-commission the prevailing boilers, pumps, pressurisation unit, controls, and many others.

Evaluate choices to transform the water system to mains fed and scope accordingly.

Proposed Electrical works:

  • Isolate and take a look at the incoming provide and essential distribution. Take a look at emergency lighting, fireplace alarm, intruder alarm, and many others. carryout a small energy take a look at and inspection.

In relation with a shortlisted contractor present a citation for the works.

With the citation accredited appoint the contractor and plan the works.

In Progress

16 July 2021

6-8 weeks work

Morgan Sindall Property Companies commissioned to undertake Part 1 works with Framework contractor:

a) Hearth security works – Consists of Hearth Compartmentalisation and fireplace doorways, (Topic to availability of fireplace doorways) work to start mid-July

Commissioning in Progress

Mid-end of August

8 weeks work

b) Water security works and remaining bundle of works and many others.- Legionella works and accessible bathroom services works

In Progress

Mid-September

4 weeks work

c) Reconnection of fuel (10-12 week lead probably) – To begin after fireplace security works full and insurers content material to permit reconnection

Works but to start out
Finish of September Reopening Date to be introduced